How Long Does a Kitchen refurbishment Take in Cranbrook?

A kitchen refurbishment in Cranbrook typically takes 4–9 weeks on site once we start. That's the build phase only — design, planning approval, building regs and material lead-times add roughly 4–8 weeks before a spade goes in.

Cranbrook projects in TN17 occasionally run longer when conservation officer comments come back on materials. We build that into our programme up front rather than discovering it mid-job.

Week-by-week programme for Cranbrook

This is the standard Gantt we issue with every Cranbrook kitchen refurbishment contract. You'll see each week's milestones in writing so progress is unambiguous.

  • Weeks 1–2: Strip out, set up, structural opening up
  • Weeks 3–2: Foundations / shell / structural
  • Weeks 3–7: First fix M&E, glazing, weathertight
  • Weeks 8–8: Second fix, joinery, plastering, tiling
  • Final week: Snagging, building control sign-off, handover

What slows a Cranbrook project down

Cranbrook's conservation requirements and the lead-time on heritage materials (peg tiles, oak, lime mortar) are the two biggest sources of delay we see. We pre-order long-lead items before we start on site to keep the programme.

  • Conservation officer requesting material samples (add 1–2 weeks)
  • Bespoke joinery lead-times — typically 4–6 weeks from sign-off
  • Engineer revisions if structural assumptions change once opened up
  • Client decision delays on finishes (we set a "lock-by" date per stage)

Get a written Cranbrook programme with your quote

Every Cranbrook project starts with a Gantt chart, lock-by dates for each stage, and a programme review every Friday on site.

Programme questions we get from Cranbrook

Can a kitchen refurbishment in Cranbrook be done faster than 4 weeks?

Occasionally — small straight refits with no structural change can run shorter, but we don't quote unrealistic programmes to win work. A 4-week minimum is what we deliver to.

Do you work on site every day in Cranbrook?

Monday to Friday 7am–5pm, Saturday morning when programme needs it. Cranbrook's residential conservation areas have noise restrictions we comply with.

What happens if you run over the programme?

Contract has liquidated damages clauses on programme slip caused by us. Weather and client variation changes are flagged in writing as they happen so the programme stays accurate.

Can we live in the house during a kitchen refurbishment in Cranbrook?

For loft conversions and most kitchen / bathroom refits — yes, with one room out of action at a time. For full house extensions opening up the back of the property, moving out for 4–6 weeks is usually easier.

In short

4–9 weeks on site for a kitchen refurbishment in Cranbrook, plus design and planning lead-time. Every project gets a written week-by-week programme up front.