How Long Does a Kitchen refurbishment Take in Ashford?
A kitchen refurbishment in Ashford typically takes 4–9 weeks on site once we start. That's the build phase only — design, planning approval, building regs and material lead-times add roughly 4–8 weeks before a spade goes in.

Ashford projects in TN23, TN24, TN25, TN26, TN27 occasionally run longer when conservation officer comments come back on materials. We build that into our programme up front rather than discovering it mid-job.
Week-by-week programme for Ashford
This is the standard Gantt we issue with every Ashford kitchen refurbishment contract. You'll see each week's milestones in writing so progress is unambiguous.
- • Weeks 1–2: Strip out, set up, structural opening up
- • Weeks 3–2: Foundations / shell / structural
- • Weeks 3–7: First fix M&E, glazing, weathertight
- • Weeks 8–8: Second fix, joinery, plastering, tiling
- • Final week: Snagging, building control sign-off, handover
What slows a Ashford project down
Ashford's conservation requirements and the lead-time on heritage materials (peg tiles, oak, lime mortar) are the two biggest sources of delay we see. We pre-order long-lead items before we start on site to keep the programme.
- • Conservation officer requesting material samples (add 1–2 weeks)
- • Bespoke joinery lead-times — typically 4–6 weeks from sign-off
- • Engineer revisions if structural assumptions change once opened up
- • Client decision delays on finishes (we set a "lock-by" date per stage)
Programme questions we get from Ashford
Can a kitchen refurbishment in Ashford be done faster than 4 weeks?
Occasionally — small straight refits with no structural change can run shorter, but we don't quote unrealistic programmes to win work. A 4-week minimum is what we deliver to.
Do you work on site every day in Ashford?
Monday to Friday 7am–5pm, Saturday morning when programme needs it. Ashford's residential conservation areas have noise restrictions we comply with.
What happens if you run over the programme?
Contract has liquidated damages clauses on programme slip caused by us. Weather and client variation changes are flagged in writing as they happen so the programme stays accurate.
Can we live in the house during a kitchen refurbishment in Ashford?
For loft conversions and most kitchen / bathroom refits — yes, with one room out of action at a time. For full house extensions opening up the back of the property, moving out for 4–6 weeks is usually easier.
Nearby areas we also cover
Get a written Ashford programme with your quote
Every Ashford project starts with a Gantt chart, lock-by dates for each stage, and a programme review every Friday on site.
Related guides
In short
4–9 weeks on site for a kitchen refurbishment in Ashford, plus design and planning lead-time. Every project gets a written week-by-week programme up front.