Tembok Carpenter & Building Services logo

How Long Does a House extension Take in Chatham?

A house extension in Chatham typically takes 12–22 weeks on site once we start. That's the build phase only — design, planning approval, building regs and material lead-times add roughly 12–20 weeks before a spade goes in.

How Long Does a House extension Take in Chatham? — example of stairs work by Tembok in Chatham

Get a Chatham quote

Free site visit. Itemised written quote in 5 working days.

Get My Free Quote

Reply within 24 hours · No obligation

Or call 07453 261303

Week-by-week programme for Chatham

This is the standard Gantt we issue with every Chatham house extension contract. You'll see each week's milestones in writing so progress is unambiguous.

  • Weeks 1–2: Strip out, set up, structural opening up
  • Weeks 3–6: Foundations / shell / structural
  • Weeks 7–17: First fix M&E, glazing, weathertight
  • Weeks 18–21: Second fix, joinery, plastering, tiling
  • Final week: Snagging, building control sign-off, handover

What slows a Chatham project down

Chatham's conservation requirements and the lead-time on heritage materials (peg tiles, oak, lime mortar) are the two biggest sources of delay we see. We pre-order long-lead items before we start on site to keep the programme.

  • Conservation officer requesting material samples (add 1–2 weeks)
  • Bespoke joinery lead-times — typically 4–6 weeks from sign-off
  • Engineer revisions if structural assumptions change once opened up
  • Client decision delays on finishes (we set a "lock-by" date per stage)

In short

12–22 weeks on site for a house extension in Chatham, plus design and planning lead-time. Every project gets a written week-by-week programme up front.

Programme questions we get from Chatham

Can a house extension in Chatham be done faster than 12 weeks?

Occasionally — small straight refits with no structural change can run shorter, but we don't quote unrealistic programmes to win work. A 12-week minimum is what we deliver to.

Do you work on site every day in Chatham?

Monday to Friday 7am–5pm, Saturday morning when programme needs it. Chatham's residential conservation areas have noise restrictions we comply with.

What happens if you run over the programme?

Contract has liquidated damages clauses on programme slip caused by us. Weather and client variation changes are flagged in writing as they happen so the programme stays accurate.

Can we live in the house during a house extension in Chatham?

For loft conversions and most kitchen / bathroom refits — yes, with one room out of action at a time. For full house extensions opening up the back of the property, moving out for 4–6 weeks is usually easier.

Nearby areas we also cover

CallWhatsAppQuote