Kitchen Refurbishment in Faversham — Step by Step from Idea to Handover

Commissioning a kitchen refurbishment in Faversham for the first time can feel opaque — a lot of homeowners tell us they signed with a builder because that builder was the only one who explained clearly what was going to happen. This page is that explanation, week by week, from first phone call to handover snag-list.

Kitchen Refurbishment in Faversham — Step by Step from Idea to Handover — example of bathroom work by Tembok in Faversham

Get a Faversham quote

Free site visit. Itemised written quote in 5 working days.

Get My Free Quote

Reply within 24 hours · No obligation

Or call 07453 261303

Stage 1 — First contact and site visit (Week 0)

You call, WhatsApp or email a brief description of what you want. We book a free 30-minute site visit within a week — usually earlier. On the visit we walk the space, take rough measurements, and give you an indicative cost band and buildability opinion. No design fee, no obligation.

Stage 2 — Written itemised quote (Weeks 1–2)

Within 5 working days of the site visit you get a written itemised quote to the Faversham address — priced against real ME13 logistics from our Biddenden yard 24 miles (~50-minute drive) away. It's fixed-price (not "from £X"), split across trade lines, VAT-inclusive, with a 10% held-back contingency.

  • Detailed spec sheet: make, model, finish for every fitting
  • Payment schedule tied to stage milestones
  • Public liability + employer's insurance certificates attached
  • Programme (Gantt) with lock-by dates for each decision

Stage 3 — Contract, drawings and planning (Weeks 2–5)

Once you accept the quote we sign a JCT Home Building Contract, take a 10% deposit, and kick off drawings. Building Control notification via Approved Inspector runs 2–3 weeks. You approve every drawing before it goes out.

Stage 4 — Material ordering (Weeks 3–5)

Long-lead items — bespoke joinery, glazing, kitchen carcases, heritage tiles — get ordered as soon as planning is signed off. On Faversham projects that means we're never waiting on materials when we start on site.

Stage 5 — Build phase (Weeks 6–6+9)

4–9 weeks on site. Weekly site meeting every Friday with a written progress note. You have real-time WhatsApp access to the project manager. Every variation goes through change control in writing before work proceeds.

  • Weeks 1–2: Strip-out, structural, foundations
  • Weeks 3–7: First fix M&E, weathertight
  • Weeks 8–8: Second fix, joinery, finishes
  • Final week: Snagging + Building Control final sign-off

Stage 6 — Snagging and sign-off (Final week)

Two rounds of snagging — one at practical completion (you walk the job and list anything), one at retention release 4 weeks later. Building Control inspects and issues final certificate. Electrical and gas certs handed over.

Stage 7 — Handover and documentation

Handover pack includes: Building Control certificate, planning approval, party wall award (if used), electrical / gas certificates, appliance manuals and warranties, workmanship warranty document, contact card for warranty claims. Everything ready to slot into your Faversham conveyancing pack if you ever sell.

Stage 8 — 5-year workmanship warranty support

Any workmanship issue in the first 5 years — we come back and put it right at no cost. Response typically same-week for non-critical, same-day for anything affecting weather-tightness or safety.

In short

Eight stages, 10–17 weeks end-to-end. Every Faversham kitchen refurbishment we run follows the same sequence, so nothing about your project should ever be a surprise.

Faversham design FAQs

How long is the full end-to-end process for a kitchen refurbishment in Faversham?

10–17 weeks typically, from first site visit to handover. Kitchen / bathroom cabinet lead-times are the biggest variable.

What do I actually have to do as the client?

Sign the contract, pay stage invoices, approve drawings, make finishes decisions by the lock-by dates in the Gantt, and walk the two snagging rounds. That's it. Everything else — planning, ordering, trade coordination, Building Control — is on us.

Can we live in the house during a Faversham kitchen refurbishment?

Usually — with one room out of action at a time.

What happens if I want to change something mid-build?

Written change control. You describe the change; we cost it; you approve in writing; then it happens. Never verbally, never mid-flow. This is how we prevent the "£X ended up as £X + 30%" scenario Faversham homeowners tell us about.